SYNERGY MFG. 870 INDUSTRIAL WAY, SAN LUIS OBISPO, CA (805) 242-0397 PPM-8012-13 JK WELD ON FRONT TRACK BAR BRACKET, STOCK TUBE Version 2 GENER
c) Weld the bottom d) Weld the top
12. Clean the welds and paint the track bar bracket and axle tube. 13. Attach the track bar and steering stabilizer or hydro ram. 14. If you want to
b) Cut the bottom welds with a cut off wheel
c) Cut the side weld, a saws all works well for this cut d) Remove the track bar bracket and grind smooth
3. Locate the new weld on track bar bracket using a 1 ½” long spacer between the lower side hole of the track bar bracket and the stock sway bar ta
4. You will be welding both sides, top and bottom of the new track bar bracket so make sure the paint is removed from those areas. 5. The bracket
This will give you a ram mounting position shown below. b) If you are using the stock JK steering knuckles, position the ram tabs as shown below.
7. If you are mounting a steering stabilizer, mount the steering stabilizer bracket as shown below. A few different mounting locations are shown;
c) Another option if using Reid Racing high steer knuckles 8. Or simply bolt on a PPM-8007 stabilizer bracket as shown below. 9. When you have
10. Make sure all of the paint is removed from the areas you will be welding the track bar bracket to the frame. 11. Reposition the track bar bracke
Comments to this Manuals